TL;DR
- Start with one controlled baseline. An RFQ is quote-ready when each bidder can identify the same technical package, price the same scenarios, disclose every exception, and use the same return fields. The NIST MEP Supplier Scouting Playbook provides a public benchmark for the technical and business input families.
- Quote buying scenarios. Separate prototypes or first articles, the first production release, recurring releases, annual planning volume, and requested price breaks. Ask for MOQ and lot multiple as their own fields.
- Control substitutions. Require every alternate material, component, process, tolerance, finish, test, or pack to appear in a deviation schedule with its evidence and commercial effect.
- Prescribe the quote return. Collect compliance, exceptions, evidence, price, timing, capacity, tooling, packaging, and import assumptions in a grid you can compare.
- Use the right shortcut. A paid, fixed-fee Tandom sourcing project can manage requirement normalization, manufacturer screening, comparable RFQs, samples, and follow-up. The buyer retains the supplier relationship and every final approval.
Release rule: do not call a quote comparable while its technical exceptions, manufacturing site, quantity basis, tooling, packing, or delivery basis are blank. A low number built on an unstated assumption is not yet a usable bid.
Apply a six-part readiness gate
Run this gate before outreach. A buyer can issue a preliminary RFQ, but the package must say which inputs are frozen, which are open, and what kind of response is expected.
If the RFQ supports an alternate-source program, keep these controls inside the broader alternative-manufacturer and second-source qualification process.
01
One technical baseline
Every file is listed with its identifier and revision. The RFQ states whether the drawing, model, BOM, or part-specific specification controls a conflict.
02
Real buying scenarios
Prototype, first release, recurring lot, annual plan, and requested price breaks are separated. Dates say whether they mean desired ship date, delivery date, or supplier proposal.
03
Visible exceptions
The supplier must answer comply, exception, or proposed alternative by requirement. Each exception carries a requirement ID, evidence, and cost or lead-time effect.
04
Evidence by phase
The RFQ says what evidence is due with the quote, before sample approval, and with production lots. It asks only for evidence relevant to the product and decision.
05
Itemized commercial basis
Currency, unit of measure, price breaks, MOQ, lot multiple, tooling, NRE, sample charges, lead-time definitions, validity, and exclusions each have a return field.
06
Cross-border assumptions
Manufacturing site, origin basis, exact delivery rule and named place, packing data, wood packaging, export charges, freight, insurance, and buyer-supplied assists are visible.
Name the owners before release
Put one owner next to each approval lane. Engineering owns the technical baseline and deviations. Quality owns inspection, test, and production evidence. Procurement owns bid rules and commercial return fields. Logistics and the importer's broker review shipment and import assumptions. The RFQ coordinator controls issue revisions and supplier questions. One person can cover several lanes, but an unnamed lane becomes an unanswered supplier question.
Control the requirement pack before outreach
Start with an index, not an attachment dump. Each row should tell a bidder what the file is, which revision applies, whether it is released or preliminary, and what decision it controls.
| Pack block | Fields to control | What the bidder must know |
|---|---|---|
| RFQ cover and issue log | RFQ ID, issue revision, issue date, response deadline with time zone, clarification cutoff, buyer contact, amendment log | Which RFQ issue the quote answers and which superseded files must be ignored |
| Part and volume schedule | Buyer part number, revision, description, unit, prototype quantity, first release, recurring lot, annual planning volume, requested price breaks | Which quantities require a firm price and which are planning scenarios only |
| Drawings and models | File name, document number, revision, native or neutral format, release status, dimensional and feature authority | Whether the 2D drawing or 3D model controls each characteristic when they differ |
| BOM and approved sources | Item number, component ID and revision, quantity per, manufacturer and part number where controlled, alternate status, buyer-supplied status | What is fixed, what can be sourced locally, and what needs an alternate proposal |
| Process, quality, and evidence | Referenced specifications, special processes, acceptance criteria, inspection or test plan, first-article need, certificates and records, evidence due phase | What must be priced, performed, submitted, and accepted before release |
| Tooling and production aids | Existing or new tooling, tool ID, process, ownership intent, marking, location, maintenance, storage, transfer, quoted life basis, buyer-supplied items | What is included in unit price, what is separate NRE, and what remains at the manufacturing site |
| Packaging and labeling | Unit protection, quantity per inner and master, labels, carton limits, pallet constraints, stackability, returnable pack, solid-wood restrictions | Which packaging is mandatory and which packed dimensions and weights must be returned |
Pack block
RFQ cover and issue log
- Fields to control
- RFQ ID, issue revision, issue date, response deadline with time zone, clarification cutoff, buyer contact, amendment log
- What the bidder must know
- Which RFQ issue the quote answers and which superseded files must be ignored
Pack block
Part and volume schedule
- Fields to control
- Buyer part number, revision, description, unit, prototype quantity, first release, recurring lot, annual planning volume, requested price breaks
- What the bidder must know
- Which quantities require a firm price and which are planning scenarios only
Pack block
Drawings and models
- Fields to control
- File name, document number, revision, native or neutral format, release status, dimensional and feature authority
- What the bidder must know
- Whether the 2D drawing or 3D model controls each characteristic when they differ
Pack block
BOM and approved sources
- Fields to control
- Item number, component ID and revision, quantity per, manufacturer and part number where controlled, alternate status, buyer-supplied status
- What the bidder must know
- What is fixed, what can be sourced locally, and what needs an alternate proposal
Pack block
Process, quality, and evidence
- Fields to control
- Referenced specifications, special processes, acceptance criteria, inspection or test plan, first-article need, certificates and records, evidence due phase
- What the bidder must know
- What must be priced, performed, submitted, and accepted before release
Pack block
Tooling and production aids
- Fields to control
- Existing or new tooling, tool ID, process, ownership intent, marking, location, maintenance, storage, transfer, quoted life basis, buyer-supplied items
- What the bidder must know
- What is included in unit price, what is separate NRE, and what remains at the manufacturing site
Pack block
Packaging and labeling
- Fields to control
- Unit protection, quantity per inner and master, labels, carton limits, pallet constraints, stackability, returnable pack, solid-wood restrictions
- What the bidder must know
- Which packaging is mandatory and which packed dimensions and weights must be returned
Publish a conflict rule
Never make the supplier decide silently between a drawing, model, BOM, and email. Write a hierarchy that fits your product. The following is a copyable structure, not a universal order:
Document conflict rule
DOCUMENT CONFLICT RULE [buyer completes]
1. Latest RFQ amendment and its change log
2. Part-specific released 2D drawing
3. Released BOM and approved-source list
4. Released 3D model for geometry not otherwise defined
5. Referenced general specifications
Supplier action:
- Stop and submit a clarification when two controlled files conflict.
- Do not price a silent interpretation.
- Record every quote assumption in the deviation schedule.Give substitutions a controlled lane
A substitution policy can be strict without blocking useful ideas. Tell bidders whether each requirement is fixed, selectable from an approved list, or open to a separately priced alternative. Require this row for every proposed change:
Deviation ID
Supplier assigns
- Requirement ID
- Drawing note, BOM line, spec clause, or pack line
- Exact proposal
- Material, component, process, dimension, test, or pack being proposed
- Reason
- Availability, manufacturability, performance, or cost rationale
- Evidence
- Cross-reference, datasheet, report, certificate, sample plan, or other requested proof
- Price effect
- Amount or no change
- Timing effect
- Effect or no change
- Buyer disposition
- Open, approved, rejected, or approved for quote only
Keep buyer disposition blank when the RFQ is issued. A proposed alternative is not accepted until the named buyer owner records a disposition. If the buyer wants both bases priced, require a compliant base quote and a separate alternate quote.
Tie evidence to the decision
Do not ask for a generic folder of certificates. For each required record, state the requirement it supports, the document or data type, who may issue it, the due phase, and the acceptance owner. Examples include a material certificate with the first production lot, a dimensional report for a first article, a process certificate for a controlled special process, or a current management-system certificate when that system is actually a qualification requirement.
Make every supplier quote into the same grid
Give bidders a return workbook or table, even if they also send their own quotation. Require N/A or not included instead of blanks. The eight blocks below are the minimum useful structure for an industrial import bid.
| Return block | Required supplier fields | Comparison control |
|---|---|---|
| 1. Supplier and site | Quoting legal entity, manufacturing legal entity, exact plant address, quote contact, subcontracted processes and sites, proposed country of manufacture | Do not evaluate a trading address as if it identifies the production site |
| 2. Technical compliance | RFQ issue, part and drawing revision, comply or exception by requirement, deviation IDs, assumptions, clarification references | A supplier cannot mark the cover sheet compliant while exceptions remain hidden in footnotes |
| 3. Price and quantity | Currency, unit of measure, unit price at each requested break, MOQ, lot multiple, minimum order value, included and excluded charges, quote validity | Map each price to a named quantity scenario and revision |
| 4. Timing and capacity | Clarification time, sample or first-article lead time, tooling lead time, production lead time, quoted capacity and its shift or equipment assumptions, current constraints | Separate manufacturing time from transit and define the clock start for every lead time |
| 5. Tooling and NRE | Line-item charge, tool or fixture description, cavities or stations where relevant, ownership proposal, physical location, life basis, maintenance, repair, replacement, storage, marking, transfer, amortization | Do not allow tooling cost or ownership to disappear inside the unit price |
| 6. Quality and evidence | Inspection and test included, first-article or sample deliverables, records included, required certificates, nonconformance path, evidence gaps, third-party charges | Every claimed capability or compliance answer points to the evidence requested for that decision |
| 7. Packaging and logistics | Units per inner and master, unit protection, carton dimensions, net and gross weight, pallet footprint and height, stackability, returnable pack, labels, solid-wood packaging status | Capture packed data, not only product dimensions and net unit weight |
| 8. Commercial and import basis | Payment proposal, warranty or remedy exceptions, delivery rule with exact named place and version, export clearance, freight and insurance treatment, assists, origin basis, duties and taxes excluded | Keep the quotation basis separate from the buyer's final customs and contract determinations |
Return block
1. Supplier and site
- Required supplier fields
- Quoting legal entity, manufacturing legal entity, exact plant address, quote contact, subcontracted processes and sites, proposed country of manufacture
- Comparison control
- Do not evaluate a trading address as if it identifies the production site
Return block
2. Technical compliance
- Required supplier fields
- RFQ issue, part and drawing revision, comply or exception by requirement, deviation IDs, assumptions, clarification references
- Comparison control
- A supplier cannot mark the cover sheet compliant while exceptions remain hidden in footnotes
Return block
3. Price and quantity
- Required supplier fields
- Currency, unit of measure, unit price at each requested break, MOQ, lot multiple, minimum order value, included and excluded charges, quote validity
- Comparison control
- Map each price to a named quantity scenario and revision
Return block
4. Timing and capacity
- Required supplier fields
- Clarification time, sample or first-article lead time, tooling lead time, production lead time, quoted capacity and its shift or equipment assumptions, current constraints
- Comparison control
- Separate manufacturing time from transit and define the clock start for every lead time
Return block
5. Tooling and NRE
- Required supplier fields
- Line-item charge, tool or fixture description, cavities or stations where relevant, ownership proposal, physical location, life basis, maintenance, repair, replacement, storage, marking, transfer, amortization
- Comparison control
- Do not allow tooling cost or ownership to disappear inside the unit price
Return block
6. Quality and evidence
- Required supplier fields
- Inspection and test included, first-article or sample deliverables, records included, required certificates, nonconformance path, evidence gaps, third-party charges
- Comparison control
- Every claimed capability or compliance answer points to the evidence requested for that decision
Return block
7. Packaging and logistics
- Required supplier fields
- Units per inner and master, unit protection, carton dimensions, net and gross weight, pallet footprint and height, stackability, returnable pack, labels, solid-wood packaging status
- Comparison control
- Capture packed data, not only product dimensions and net unit weight
Return block
8. Commercial and import basis
- Required supplier fields
- Payment proposal, warranty or remedy exceptions, delivery rule with exact named place and version, export clearance, freight and insurance treatment, assists, origin basis, duties and taxes excluded
- Comparison control
- Keep the quotation basis separate from the buyer's final customs and contract determinations
Copy this quote cover
Supplier quote cover
SUPPLIER QUOTE RETURN
Buyer RFQ ID / issue: ______________________________
Supplier quote number / date: ______________________
Quote valid through: _______________________________
Quoting legal entity: ______________________________
Manufacturing legal entity and site: _______________
Currency / unit of measure: ________________________
Delivery basis: [rule] [named place or point] Incoterms 2020
Supplier contact / email: ___________________________
Technical response status [choose one]:
[ ] Comply, no exceptions
[ ] Comply except for attached deviation schedule
[ ] Budgetary only, open assumptions attached
Supplier confirmation:
All blanks are marked N/A or not included: [ ] Yes
All proposed substitutions are in the deviation schedule: [ ] Yes
All quote exclusions are listed: [ ] YesUse one line for each price break
These fields are columns, not separate rows. Use one row for every unique part, revision, and quantity break so each unit price keeps its exact basis. Copy the column set, then paste it into cell A1 in Excel, Google Sheets, or a sourcing system.
Price-break return columns
Copies 23 columns as tab-separated cells for Excel and Google Sheets.
Columns
- 1
buyer_part_number - 2
part_revision - 3
requirement_pack_issue - 4
price_break_quantity - 5
unit_of_measure - 6
currency - 7
unit_price - 8
MOQ - 9
lot_multiple - 10
minimum_order_value - 11
unit_price_inclusions - 12
tooling_charge - 13
other_NRE - 14
sample_or_first_article_charge - 15
sample_lead_time - 16
tooling_lead_time - 17
production_lead_time - 18
capacity_quantity - 19
capacity_period - 20
quote_valid_through - 21
deviation_ids - 22
evidence_gaps - 23
commercial_exceptions
After the fields return, the commercial readiness guide shows how to reconcile MOQ, tooling, lead-time definitions, payment controls, and capacity evidence against the buyer's demand scenario.
Expose the assumptions that move landed cost
A supplier quote is not a customs entry or a landed-cost model. Still, the RFQ should collect the facts that will later shape freight, valuation, origin review, and entry planning. This matters whether the manufacturing search spans Asia, Latin America, or both.
Write a complete delivery basis
The ICC's official Incoterms 2020 checklist and flowcharts provide a current starting point for choosing a rule and warn that a general flowchart cannot decide a real transaction by itself. For a comparable quote, ask for [rule] [named place or point] Incoterms 2020, then list freight, insurance, export clearance, destination charges, duty, and tax inclusions separately. The named point affects the buyer's cost and risk model, and Incoterms does not replace the rest of the sale contract.
Separate plant, manufacture, and origin
Require the exact manufacturing site, proposed country of manufacture, and the supplier's factual basis for any origin statement. Do not use the sales office, ship-from warehouse, or supplier assertion as the buyer's final US country-of-origin determination. The importer and its broker or counsel should validate origin and classification against the real production facts.
If the seller, plant, exporter, payee, or intermediary roles are not yet clear, resolve them with the manufacturer identity and capability workflow before treating a quote as site-specific evidence.
Capture packing, charges, and assists
US commercial-invoice rules in 19 CFR 141.86 call for detailed descriptions, quantities, price and currency, itemized charges, origin, packing detail, and certain assists. Transaction-value rules in 19 CFR 152.103 address packing and assists such as tools, dies, and molds. Collect those fields during the bid, then let the importer and broker make the transaction-specific valuation decision.
| Field | Supplier prompt | Buyer use |
|---|---|---|
| Manufacturing site | Legal entity and street address where final production occurs; list material subcontract sites | Supplier screening, routing, origin review, and site-specific follow-up |
| Origin assumption | Proposed country and the material, component, and process facts supporting that statement | Input for importer and broker review, not an automatic determination |
| Delivery basis | Rule, exact named place or point, and Incoterms 2020; state export-clearance, freight, and insurance inclusions | Places quotes on a visible handoff and cost basis |
| Packed shipment data | Inner, carton, and pallet quantities; dimensions; net and gross weights; stackability; shipment-size assumptions | Supports a separate freight and landed-cost scenario |
| Wood packaging | Identify solid-wood pallets, crates, reels, or dunnage and confirm current US-compliant treatment and marking | Packaging approval and import-readiness follow-up |
| Buyer-supplied items | List tools, dies, molds, engineering, components, or other items supplied free or below cost and show whether unit price includes them | Commercial normalization and later customs-valuation review |
Field
Manufacturing site
- Supplier prompt
- Legal entity and street address where final production occurs; list material subcontract sites
- Buyer use
- Supplier screening, routing, origin review, and site-specific follow-up
Field
Origin assumption
- Supplier prompt
- Proposed country and the material, component, and process facts supporting that statement
- Buyer use
- Input for importer and broker review, not an automatic determination
Field
Delivery basis
- Supplier prompt
- Rule, exact named place or point, and Incoterms 2020; state export-clearance, freight, and insurance inclusions
- Buyer use
- Places quotes on a visible handoff and cost basis
Field
Packed shipment data
- Supplier prompt
- Inner, carton, and pallet quantities; dimensions; net and gross weights; stackability; shipment-size assumptions
- Buyer use
- Supports a separate freight and landed-cost scenario
Field
Wood packaging
- Supplier prompt
- Identify solid-wood pallets, crates, reels, or dunnage and confirm current US-compliant treatment and marking
- Buyer use
- Packaging approval and import-readiness follow-up
Field
Buyer-supplied items
- Supplier prompt
- List tools, dies, molds, engineering, components, or other items supplied free or below cost and show whether unit price includes them
- Buyer use
- Commercial normalization and later customs-valuation review
If solid-wood pallets, crates, reels, or dunnage are proposed, verify the current USDA APHIS wood packaging requirements before shipment. Once the buyer has a reviewed HTS code, origin, value, and shipment facts, the free Tandom Duty Calculator can model supported US duty layers and fees. That estimate does not approve the supplier or replace the importer's final determinations.
Worked example: one bracket, one controlled baseline
Illustrative template only. This example does not describe a Tandom customer, quote, supplier, price, result, or case study. All identifiers and quantities below are fictional and symbolic; they show how to structure an RFQ response.
The buyer is requesting quotes for a machined mounting bracket. The controlled part is BRKT-042 Rev C. Instead of sending a STEP file and an annual quantity in an email, the buyer issues this baseline:
| RFQ field | Illustrative entry | Supplier return required |
|---|---|---|
| Issue control | EX-RFQ-017, issue 0; response must identify this issue | Confirmed RFQ issue and quote revision |
| Part baseline | BRKT-042 Rev C; released 2D PDF and STEP model Rev C | Confirmed part, drawing, and model revision |
| Document authority | 2D drawing controls material, tolerances, threads, finish, and inspection notes; STEP controls geometry not otherwise defined | Conflict questions or explicit compliance |
| Quote scenarios | 10 development pieces, first release of 250, annual planning volume of 2,000; price breaks at 250, 500, and 1,000 | One row per break, plus MOQ and lot multiple |
| Substitutions | No silent material, finish, tolerance, process, or packaging substitution; separately priced proposals allowed through deviation schedule | Compliant base quote plus every alternate as a deviation |
| Evidence | Material record and first-article dimensional report are required at the phase stated in the RFQ quality schedule | Included deliverables, format, timing, and any charge or exception |
| Tooling and NRE | Itemize every fixture, gage, programming, and other NRE; do not bury it in unit price | Description, amount, ownership proposal, location, maintenance, and transfer treatment |
| Packaging | Individually protect finished surfaces; proposed master-pack quantity subject to buyer approval | Pack method, quantities, carton and pallet dimensions, net and gross weights, wood packaging status |
| Import basis | Supplier returns manufacturing site and one delivery basis using rule, named point, and Incoterms 2020 | Origin facts, export and freight inclusions, quote exclusions, and buyer-supplied assists |
RFQ field
Issue control
- Illustrative entry
- EX-RFQ-017, issue 0; response must identify this issue
- Supplier return required
- Confirmed RFQ issue and quote revision
RFQ field
Part baseline
- Illustrative entry
- BRKT-042 Rev C; released 2D PDF and STEP model Rev C
- Supplier return required
- Confirmed part, drawing, and model revision
RFQ field
Document authority
- Illustrative entry
- 2D drawing controls material, tolerances, threads, finish, and inspection notes; STEP controls geometry not otherwise defined
- Supplier return required
- Conflict questions or explicit compliance
RFQ field
Quote scenarios
- Illustrative entry
- 10 development pieces, first release of 250, annual planning volume of 2,000; price breaks at 250, 500, and 1,000
- Supplier return required
- One row per break, plus MOQ and lot multiple
RFQ field
Substitutions
- Illustrative entry
- No silent material, finish, tolerance, process, or packaging substitution; separately priced proposals allowed through deviation schedule
- Supplier return required
- Compliant base quote plus every alternate as a deviation
RFQ field
Evidence
- Illustrative entry
- Material record and first-article dimensional report are required at the phase stated in the RFQ quality schedule
- Supplier return required
- Included deliverables, format, timing, and any charge or exception
RFQ field
Tooling and NRE
- Illustrative entry
- Itemize every fixture, gage, programming, and other NRE; do not bury it in unit price
- Supplier return required
- Description, amount, ownership proposal, location, maintenance, and transfer treatment
RFQ field
Packaging
- Illustrative entry
- Individually protect finished surfaces; proposed master-pack quantity subject to buyer approval
- Supplier return required
- Pack method, quantities, carton and pallet dimensions, net and gross weights, wood packaging status
RFQ field
Import basis
- Illustrative entry
- Supplier returns manufacturing site and one delivery basis using rule, named point, and Incoterms 2020
- Supplier return required
- Origin facts, export and freight inclusions, quote exclusions, and buyer-supplied assists
How the deviation row prevents a false match
Suppose a bidder proposes a locally available alternate material. The supplier does not replace the RFQ material in its base price without comment. It returns a compliant base row and a separate D-01 row naming the affected drawing note, exact alternative, rationale, cross-reference or test evidence, and price and timing effects. The buyer's engineering owner can then approve, reject, or keep the alternate open. Until that disposition is recorded, the alternate price is not compared as technically equal.
When the RFQ calls for a sample or first-article record, use the sample validation, FAI, and PPAP guide to define what the evidence can prove and who records acceptance.
Release the comparison only when gaps are closed
- Every supplier response identifies EX-RFQ-017 issue 0 and BRKT-042 Rev C.
- Every requested quantity break has a price, MOQ, lot multiple, and unit of measure.
- All exceptions and alternates point to a deviation ID with evidence and commercial effect.
- Tooling, quality deliverables, packaging, site, and delivery basis are returned or marked not included.
- The buyer compares the compliant base rows first and evaluates proposed alternates separately.
The next step is to normalize the returned rows. Use the supplier quote comparison guide to separate technical equivalence, commercial terms, tooling, packing, and landed-cost assumptions before a sourcing decision.
Common pitfalls
Most RFQ failures show up later as a requote, an invalid comparison, or an approval gap. Catch them before the supplier prices the work.
Files have names but no controlled revisions
A bidder quotes final.step while the buyer evaluates Rev C. The price and feasibility response are tied to the wrong geometry, so the row must be corrected or requoted before comparison.
The drawing and model disagree without an authority rule
One bidder follows the model and another follows the drawing. Both may say they comply, but they did not quote the same requirement. Issue a clarification or amendment instead of choosing the preferred answer.
Annual volume is mistaken for one release
A supplier prices the entire forecast as one lot. The apparent unit price hides a larger MOQ, order value, and inventory commitment than the buyer planned. Separate annual planning volume from release sizes.
Silence is treated as approval for substitutions
A lower bid uses a different material, component, process, or pack without a deviation row. The quote cannot be treated as technically equal until the exact change is disclosed and reviewed.
Evidence is postponed until after supplier selection
Inspection reports, certificates, tests, or first-article work appear as new scope after the bid. Pricing and lead times must be reopened, and the selected supplier may not support the required record.
Tooling is buried inside unit price
The buyer cannot tell what was paid for, who is meant to own it, where it will stay, or how repair and transfer work. That ambiguity blocks a clean commercial comparison and can frustrate future second sourcing.
Packaging is reduced to one word
“Export pack” does not reveal carton count, packed dimensions, gross weight, stackability, surface protection, or wood packaging. Freight modeling and packaging approval remain open after the quote arrives.
The quote says FOB without a named point
Suppliers can price different handoff locations and cost inclusions under the same three letters. The rows look aligned but are not on the same delivery basis. Require the exact named place and version.
The supplier address is treated as country of origin
A sales office or ship-from address does not establish where production occurred or the US origin result. The landed-cost screen is unreliable until manufacturing facts and origin assumptions are reviewed.
Free-form quotes are accepted with blank fields
A blank is read as no charge, no exception, or full compliance. The buyer later discovers it meant not reviewed. Map the response into the return schedule and send every gap back for written confirmation.
Glossary
- Request for quotation (RFQ)
- A buyer's request for a supplier to price a defined requirement and return stated technical and commercial information.
- Requirement pack
- The indexed set of drawings, models, BOMs, specifications, quality requirements, volumes, tooling, packaging, and bid instructions that define what is being quoted.
- Controlled document
- A document identified by a unique number or file name, revision, release status, and change authority so users can distinguish the current version from obsolete ones.
- Revision baseline
- The exact set of document and part revisions that one RFQ issue and its supplier responses must reference.
- Bill of materials (BOM)
- The component and material list for a part or assembly, normally including item number, identifier, revision, quantity per, and any controlled source information.
- Approved source list
- The manufacturers, supplier part numbers, or defined options the buyer has already approved for a BOM line. It should say whether alternates may be proposed.
- Deviation
- A documented difference between the RFQ requirement and the supplier's proposed product, process, evidence, timing, packaging, or commercial basis.
- Substitution
- A proposed alternate material, component, process, finish, test, or pack. A proposal is not approval until the named buyer owner records a disposition.
- Evidence schedule
- A list that ties each required record or proof to a requirement, issuer, due phase, acceptance criteria, and buyer owner.
- Non-recurring engineering (NRE)
- A one-time engineering, programming, setup, test-development, or similar charge that should be separated from recurring unit price.
- Tooling
- Molds, dies, fixtures, gages, patterns, jigs, and other production aids whose cost, ownership, location, maintenance, life basis, and transfer treatment may need separate agreement.
- Minimum order quantity (MOQ)
- The minimum quantity a supplier will accept for an order or release. It is different from annual planning volume and from a packaging lot.
- Lot multiple
- The increment in which quantities must be ordered above the minimum, often driven by process, material, or packaging constraints.
- First article
- An initial production-representative item and associated records used for buyer review before broader production. The buyer must define the format, scope, and approval effect required for the product.
- Incoterms named place
- The port, place, or point written with an Incoterms rule and version. It helps define delivery, risk, and cost allocation under that rule.
- Assist
- Certain goods or services a buyer supplies directly or indirectly for production, such as some tools, dies, molds, or engineering, that may require customs-valuation review.
FAQ
Practical answers for buyers turning incomplete part information into a quote-ready manufacturing package.